Tuesday, April 20, 2021

Getting Closer...

Few updates to share:

  1. We found out that we have to include a NFPA 13D fire suppression system as a part of the build, as all homes in this development are required to have it installed (though nothing was called out in the purchase docs, CC&Rs, etc.)  UGH... that was a budget hit we were not prepared for, so we quickly had to work through it.  In the end, it will be good and add "peace-of-mind," but not something we had planned on. 
  2. We will sign with title TONIGHT, so that part will be completed! (No clue what took so long...)
  3. Got this update from Mike (builder) this morning:  "I’m working hard to have the dig out next week." 

So, I am hoping to start having plenty of updates/pictures to share soon!  We simply cannot wait!